| Learning Outcome | Learning Outcome Code | Compulsory/Elective | Duration (Hours) |
|---|---|---|---|
| Apply Safe Working Practices | CON/0805/OC1 | Compulsory | 30 |
| Make electrical wire joints & soldering | CON/0805/OC2 | Compulsory | 30 |
| Analyse, demonstrate and test basic electrical connection | CON/0805/OC3 | Compulsory | 30 |
| Describe the process of erecting and dismantling of 3.6 Meters Scaffolds | CON/0819/OC1 | Compulsory | 30 |
| Plan and prepare Earthing installation | CON/0805/OC4 | Compulsory | 60 |
| Assemble, install and test wiring system & lighting arrangement | CON/0819/OC2 | Compulsory | 60 |
| Plan and execute temporary electrical connection to a working site | CON/0819/OC3 | Compulsory | 60 |
| OJT | CON/0819/OC4 | Compulsory | 60 |
| Employability Skill | DGT/VSQ/N0102 | Compulsory | 60 |